Status of LNG Terminal Construction

(As of Feb. 28, 2024)
Status of LNG Terminal Construction - Project, Scale of Features, Period, Remarks
Project Scale of Features Period Remarks
Dangjin Dangjin Terminal Construction
(Phase 1)
  • 270,000 kl storage tank x 4 units
  • Regasification/transmission facility :
    • 1,560 tons/h
    • Seawater type : 180 tons/h × 4units
    • Combustion type : 120 tons/h × 7units
  • Berthing dock: 1 for a 270,000 kl LNG carrier
  • Unloading dock: 1 fitted with an unloading arm
Dec. 2019 ~ Dec. 2025
Dangjin Terminal Construction
(Phase 2)
  • 270,000 kl storage tank x 3 units
  • Substation 1 building
Jul. 2022 ~ Oct. 2028

Status of Gas Supply Pipeline Construction

(As of Feb. 28, 2024)
Status of LNG Terminal Construction - Business name, Business name, period, Remarks
Business name Business name period Remarks
Construction project in an unsupplied area
  • The main pipe : 166km
  • 8 Stations
Jan. 2024 ~ Dec. 2026 Wanju-gun, Sari~Goesan, Gasan~Gapyeong, Jangheung~Boseong, HDENF
Pressure reinforcement construction, etc
  • The main pipe : 273km
  • 22 Stations
Jan. 2024 ~ Dec. 2026 Pyeongtaek~Ansan, Pyeongtaek~Osan, Cheongju~Sari, Wanju~Jinan, Dangjin~Bugok, Oseong~Beolgyo, Oeryong~Bonghwa

Aerial View of LNG Terminal

( As of 2021.3.31)
  • Storage Tank: 23 in Operation

    Pyeongtaek (Storage Tank : 23 in Operation)

  • Storage Tank: 23 in Operation

    Inchen (Storage Tank : 23 in Operation)

  • Storage Tank: 7 in Operation

    Tongyeong (Storage Tank : 17 in Operation)

  • Storage Tank: 12 in Operation

    Shamcheck (Storage Tank : 12 in Operation)

  • Storage Tank: 2 in Operation

    Jeju (Storage Tank : 2 in Operation)

  • Storage tanks: 4 under construction

    Dangjin (Storage tanks : 4 under construction)