LNG Terminal

LNG imported into Korea by LNG carriers from natural gas producing countries around the world is unloaded at LNG Terminals, stored in storage tanks, regasified; and distributed through the nationwide pipeline network.

(As of Jan.1, 2022)

Move left and right

Factor, Pyeongtaek Terminal, Incheon Terminal, Tongyeong Terminal, Samcheok Terminal, Jeju Terminal,Total
Facility Pyeongtaek Terminal Incheon Terminal Tongyeong Terminal Samcheok Terminal Jeju Terminal Total
Start of Operations Nov. 1986 Oct. 1996 Sept. 2002 July 2014 Oct. 2019 -
Area 133.2 ha 138.2 ha 112.4 ha 87.3 ha 7.6 ha -
Storage Tanks
  • 100,000㎘ x 10
  • 140,000㎘ x 4
  • 200,000㎘ x 9
  • 100,000㎘ x 10
  • 140,000㎘ x 2
  • 200,000㎘ x 11
  • 140,000㎘ x 13
  • 200,000㎘ x 4
  • 200,000㎘ x 9
  • 270,000㎘ x 3
45,000㎘ x 2 77 tanks, 12.16 mil.kL
LNG Pump Low Pressure Pump 150T/H x 59
  • 150T/H x 52
  • 200T/H x 9
150T/H x 41 150T/H x 36 32T/H x 6
  • 32T/H x 6
  • 150T/H x 188
  • 200T/H x 9
High Pressure Pump 110T/H x 43 110T/H x 58 110T/H x 29 110T/H x 12 25T/H x 4
  • 25T/H x 4
  • 110T/H x 142
Vaporizer Low pressure ORV 90T/H x 3 - - - - 90T/H x 3
High pressure ORV 180T/H x 13
  • 180T/H x 8
  • 240T/H x 1
180T/H x 12 180T/H x 6 -
  • 180T/H x 39
  • 240T/H x 1
SCV
  • 90T/H x 10
  • 120T/H x 12
  • 90T/H x 21
  • 120T/H x 22
  • 90T/H x 3
  • 120T/H x 5
120T/H x 2 60T/H x 1
  • 60T/H x 1
  • 90T/H x 34
  • 120T/H x 41
AAV - - - - 15T/H x 4 15T/H x 4
Recondenser
  • 30T/H x 2
  • 40T/H x 1
  • 60T/H x 1
  • 26.1T/H x 1
  • 30T/H x 4
  • 40T/H x 1
  • 17T/H x 2
  • 21T/H x 2
40T/H x 2 5T/H x 1
  • 5T/H x 1
  • 17T/H x 2
  • 21T/H x 2
  • 26.1T/H x 1
  • 30T/H x 6
  • 40T/H x 4
  • 60T/H x 1
BOG Processing Facility 12,000N㎥/H x 14 12,000N㎥/H x 14 12,000N㎥/H x 10 12,000N㎥/H x 6 3,500N㎥/H x 3
  • 12,000N㎥/H x 4
  • 3,500N㎥/H x 3
Seawater Pump for Vaporization
  • 10,000N㎥/H x 14
  • 5,000N㎥/H x 1
  • 12,000N㎥/H x 4
  • 10,000N㎥/H x 5
  • 5,000N㎥/H x 1
  • 10,000N㎥/H x 12
  • 5,000N㎥/H x 2
  • 12,000N㎥/H x 5
  • 6,000N㎥/H x 1
-
  • 5,000N㎥/H x 4
  • 6,000N㎥/H x 1
  • 10,000N㎥/H x 31
  • 12,000N㎥/H x 9
Jetty
  • 75,000 tons: 1 vessel
  • 127,000 tons: 1 vessel
  • 75,000 tons: 1 vessel
  • 127,000 tons: 1 vessel
  • 75,000 tons: 1 vessel
  • 127,000 tons: 1 vessel
27,000 tons: 1 vessel 6,500 tons: 1 vessel
  • 6,500 tons: 1 vessel
  • 75,000 tons: 3 vessel
  • 127,000 tons: 4 vessel

Aerial View of LNG Terminal

  • Pyeongtaek Terminal

    Pyeongtaek LNG Terminal

  • Incheon Terminal

    Incheon LNG Terminal

  • Tongyeong Terminal

    Tongyeong LNG Terminal

  • Samcheok Terminal

    Samcheok LNG Terminal

  • Jeju Terminal

    Jeju LNG Terminal

Affiliated Homepage Shortcut Button Kids KOGAS
Homepage language selection button EN
close