Status of LNG Terminal Construction

(As of Feb 27, 2026)
Status of LNG Terminal Construction - Project, Scale of Features, Period, Remarks
Project Scale of Features Period Remarks
Dangjin Dangjin Terminal Construction
(Phase 1)
  • 270,000 kl storage tank x 4 units
  • Regasification/transmission facility :
    • 1,560 tons/h
    • Seawater type : 180 tons/h × 4units
    • Combustion type : 120 tons/h × 7units
  • Berthing dock: 1 for a 270,000 kl LNG carrier
  • Unloading dock: 1 fitted with an unloading arm
Dec. 2019 ~ May. 2027
Dangjin Terminal Construction
(Phase 2)
  • 270,000 kl storage tank x 3 units
  • Substation 1 building
Jul. 2022 ~ Dec. 2029

Status of Gas Supply Pipeline Construction

(As of Feb 27, 2026)
Status of LNG Terminal Construction - Business name, Business name, period, Remarks
Business name Business name period Remarks
Construction project in an unsupplied area
  • The main pipe : 94km
  • 10 Stations
Jan. 2026 ~ Oct. 2028 Gasan-Gapyeong, Gongju Combined Cycle Power Plant, Suwon Combined Heat & Power Plant
Pressure reinforcement construction, etc
  • The main pipe : 177km
  • 11 Stations
Jan. 2026 ~ Nov. 2029 Oeryong-Bonghwa,, Dangjin-Bugok, Boseong-Beolgyo

Aerial View of LNG Terminal

(As of Feb 27, 2026)
  • Storage Tank: 23 in Operation

    Pyeongtaek (Storage Tank : 23 in Operation)

  • Storage Tank: 23 in Operation

    Inchen (Storage Tank : 23 in Operation)

  • Storage Tank: 7 in Operation

    Tongyeong (Storage Tank : 17 in Operation)

  • Storage Tank: 12 in Operation

    Shamcheck (Storage Tank : 12 in Operation)

  • Storage Tank: 2 in Operation

    Jeju (Storage Tank : 2 in Operation)

  • Storage tanks: 4 under construction

    Dangjin (Storage tanks : 7 under construction)